Pay applications
8 min readAll explainers

G702 / G703 payment applications explained — for subcontractors chasing GC payment.

What AIA G702 and G703 payment applications actually are, when subcontractors file them, where conditional vs. unconditional lien waivers fit in the monthly billing cycle, the six paperwork mistakes that stall pay apps on the GC's desk, and how Johnston Admin Management Services runs them at $45/hour, billed to the exact minute through Clockify.

Written by Johnston Admin Management Services LLC · Virginia HQ, U.S. nationwide.
Section 1

What AIA G702 actually is

AIA G702 — formally titled Application and Certificate for Payment— is the contractor-facing cover sheet that summarizes a billing cycle. It is a single one-page form the GC hands to the owner or owner's lender for funding. Think of it as the receipt for one month of construction work.

The G702 carries six totals: the original contract sum, the running total of work completed to date, retainage currently held, the current payment due this period, and the signature lines the contractor and the architect / owner rep use to certify that the amount is correct. When the owner rep signs the G702, they are certifying the whole month's billing to the lender or owner — once the lender funds the draw, the GC's job is to push that money down through the subcontractor pay apps that built it up.

For subcontractors, your G702 lives inside the GC's G702. The GC pulls each sub's G703 (the schedule-of-values breakdown — Section 2 below) and rolls the totals into the GC's G702. If your G703 lines don't reconcile to the totals you agree on with the GC, that single unreconciled line is the most common reason your pay app stalls on the owner rep desk for weeks. We run the G703 → G702 reconciliation on every pay app we ship at the firm — it is one of the reasons subs stop chasing the GC's desk and start getting paid on the cadence the contract sets.

Section 2

What G703 is — the continuation / schedule-of-values sheet

AIA G703 — the Continuation Sheet — is the multi-line schedule-of-values breakdown that goes behind the G702. Every line item on the schedule of values gets its own row on the G703: a description, the scheduled value, the work completed this period, work completed to date, materials stored (and not yet installed), retainage, and the balance remaining to finish.

The G703 is where the paperwork actually lives. If your scope is 47 line items across rough-in, trim-out, and final, the G703 is 47 rows that each have to add up correctly — both within themselves (work this period + work previously + stored + retainage = scheduled value) and rolling up to the G702 totals (otherwise the owner rep kicks it back). When a subcontract carries 100+ line items, building a G703 by hand on the 25th of every month is a non-trivial amount of work — the kind of work that scales well when it is run on a Clockify-tracked rate instead of being absorbed into a project manager's weekend.

One pay app, six paperwork pieces

The G702 / G703 pay app ships as a stack — not just the two forms.

  • G702 — cover sheet (contractor + owner rep signatures).
  • G703 — continuation sheet (every SOV line, this period and to-date).
  • Conditional lien waiver — for the current payment due.
  • Stored-materials backup — bills of sale + insurance rider for stored-not-yet-installed line items, where applicable.
  • Schedule-of-values reconciliation— sub's SOV lines match the GC master SOV.
  • Project status / progress photos — owner rep often requests, depending on contract.
Section 3

When subcontractors file them

Monthly — one pay app per billing cycle, on the schedule the subcontract sets in its scope. The first pay app usually lands the month work begins, with the mobilization line items and any pre-bought / stored materials running as the project progresses. The final pay app ships at substantial completion / project closeout, paired with the wrap-up paperwork stack (G704 certificate of substantial completion, G706 / G706A contractor / architect affidavits of final payment) and the conditional lien waiver for the final draw.

In practice three things drive the actual cadence — none of them the calendar: (1) the schedule of values the GC approved at job start, which sets the line items you bill against; (2) the GC's billing cutoff, which is the date your pay app has to land in their billing inbox to make the current draw; and (3) the owner's lender draw schedule, which is the date the GC's G702 has to hit the owner or construction loan officer to actually trigger funding. Miss any of those three by a couple of days and your pay app slips to the next draw — which is 30 more days of float on working capital.

The sub who ships the G702 / G703 stack 3-5 business days BEFORE the GC's billing cutoff is the sub who gets paid on time. That is why we build the pay app on a standing monthly schedule — once the GC confirms the cutoff calendar, the internal Clockify task for “build next month's G703 + G702 + waiver” is queued for the same week, every month, until substantial completion.

Section 4

Where conditional vs. unconditional waivers fit in the cycle

The lien-rights sequencing is the part of the workflow most subs get wrong, and the part most generic bookkeepers miss entirely. The four-waiver pattern runs:

Progress pay app #1

Conditional waiver for current draw

Files WITH the G702 (cover) + G703 (continuation). Releases lien rights only if and when the funds in this pay app actually clear. This is the productive waiver — it lets work continue on the project while the funds are in flight.

Progress pay app #1

Unconditional waiver for PRIOR draw

Files with the current pay app (sometimes after). Releases lien rights for the previous period's funds unconditionally — i.e. claims the previous funds were actually received. The handshake here is what a state lien-rights statute or contract provision is built on.

Final pay app

Conditional waiver for final draw

Files WITH the final G702 / G703 (closeout cycle). Releases lien rights only if and when the funds in the final draw are actually received. This is what most subs file at closeout — and stops here.

After final funds clear

Unconditional waiver for final draw

Generated and delivered only after the funds in the final draw actually clear the bank. The unconditional waiver releases lien rights the moment the sub signs it — so filing it before funds have cleared is the most expensive lien-rights mistake a sub can make.

We hold the unconditional waivers until the corresponding funds clear — exactly the same flow we run for subs who don't want to accidentally release lien rights before the money has arrived. Most lien-rights misfires in the field trace back to one specific decision: the unconditional waiver signed two weeks before the funds cleared.

Section 5

Six mistakes that stall pay apps on the GC's desk

These are the same six reasons pay apps get kicked back month after month, across enough GC relationships to stop being coincidence. Every one of them is fixable in the paperwork itself — and every one of them costs a sub 2-4 weeks of float.

Mistake #1

G703 lines don't reconcile to the G702 totals.

The sum of work-completed-to-date across all G703 lines is supposed to equal the G702's “work completed to date” line — to the cent. When it doesn't, the owner rep kicks the whole stack back, the GC re-queues your billing into next month, and the float grows by 30 days. This is fixable with a 5-line reconciliation check before the file ever ships.

Mistake #2

Stored-materials values are claimed without backup.

The G703 has a column for materials stored but not yet installed — and it is the single most abused line on the form. Without a bill of sale AND a builder's risk / installation-floater insurance rider on those stored materials, the owner rep cannot certify they exist or are covered if they burn down in the yard. Always include both — and check your contract's stored-materials clause, because some GCs cap stored-material certs at 50% of the line value or exclude certain material categories.

Mistake #3

Retainage is calculated inconsistently from the contract.

The AIA G702/G703 default is 10% retainage until 50% project completion, then zero going forward — but most subcontracts override this. If your subcontract holds 10% retainage across the entire project (or a different percentage, or a different split point), the G702 / G703 needs to match the contract, not the AIA default. Getting this wrong charges the GC the wrong amount and backwards-bills the sub at closeout for the difference.

Mistake #4

Lien waivers are missing or paired wrong (conditional / unconditional).

The most expensive version is an unconditional waiver filed with the final pay application — the sub signs away lien rights before the funds clear. Other versions include a missing waiver (the owner rep holds the entire pay app until the waiver is supplied), or an unconditional filed for a progress draw (releasing lien rights on funds that haven't arrived yet). Run Section 4 above before you sign anything.

Mistake #5

Schedule-of-values line names don't match the GC's master SOV.

If your G703 calls “Line 7: Drywall — Hang” and the GC's master SOV calls it “Line 7: GWB Hang & Finish,” the owner rep cannot reconcile your pay app to the contractor's master and will bounce it. Lock the SOV naming at job start and never change it without a written change order.

Mistake #6

Missing the owner's lender draw date.

The construction loan draw date is the actual funding trigger — the GC's G702 has to be in the lender's hands BEFORE that date or the entire billing cycle moves forward to next month's draw. Many subs only track the GC's billing cutoff and miss the lender draw by a day, pushing working capital out 30 days unnecessarily. Track both dates and build the pay app backward from the draw, not forward from the calendar.

Section 6

How we run them — and what we quote

Johnston Admin Management Services builds and submits the G702 / G703 pay app stack from the PO forward. The day your contract or scope arrives, we open a Clockify project for the engagement and a recurring monthly task for the next pay app cycle. From that point forward every minute we touch the paperwork — pulling the schedule of values, building the G703 lines, applying retainage per contract, attaching the conditional lien waiver, reconciling the G702 totals — logs on its own Clockify line.

Every minute is billed at $45/hour to the exact minute. If 14 minutes go into a pay-app task, you pay for 14 minutes — not a 15-minute block, not a quarter-hour, not a padded estimate. The invoice you receive reconciles line-by-line to the Clockify entries behind it, with no minimum purchase and no surprise billing. Most monthly pay apps ship in 30-90 minutes of total admin time; the unconditional waiver for the final draw adds a short task at the end of the project.

What the typical invoice looks like

Pull schedule of values + previous pay app

9 min

Build G703 lines — work this period + to-date

26 min

Apply retainage per contract + G703 → G702 reconcile

12 min

Attach conditional lien waiver + stored-materials backup

11 min

Submit to GC + A/R follow-up cadence setup

8 min

Total — 66 min × $45/hr

$49.50

One pay app, one invoice, one $45/hour Clockify-tracked price — every minute visible before the invoice goes out. No padded estimates, no quarter-hour rounding, no minimum purchase, no agency markup.

The unconditional final waiver ships at the end of the project, after the funds in the final draw actually clear — same Clockify rate, same line-item invoice. We work from the contract or scope the sub sends, no separate onboarding packet, and we confirm project coverage by zip before the first timer starts. To see the full service menu (pay apps, A/R follow-up, full-fixture virtual bookkeeping) drop into the services page.

FAQ

Frequently asked questions.

What is an AIA G702?

AIA G702 — formally "Application and Certificate for Payment" — is the contractor-facing cover sheet that summarizes a billing cycle. It shows the contract sum to date, the work completed to date, retainage held, the current payment due, and the signature lines the contractor and the architect / owner rep use to certify the amount. It is the single one-page summary the GC signs and forwards to the lender or owner for funding.

What is an AIA G703?

AIA G703 — "Continuation Sheet" — is the multi-line schedule-of-values breakdown that goes behind the G702. It shows every line item on the schedule of values, the scheduled value, work completed this period, work completed to date, materials stored (and not yet installed), retainage, and the balance to finish. Every line number on the G703 has to roll up cleanly to the totals on the G702 — a line that does not reconcile is the most common reason pay apps stall on the owner rep desk.

When does a subcontractor file a G702/G703 pay app?

Monthly — one pay app per billing cycle, on the schedule the subcontract sets in its scope. The first pay app usually ships the month work begins, with stored-materials line items carried as the project progresses. The final pay app ships at substantial completion / project closeout, paired with the wrap-up paperwork (G704 certificate of substantial completion, G706 / G706A contractor / architect affidavits of final payment) and the conditional lien waivers for that cycle.

Where do conditional vs. unconditional lien waivers fit in the flow?

Conditional waivers ship WITH each pay app — they release lien rights once the funds in that application are received. Unconditional waivers are NOT filed with the final pay application; they are generated and delivered only after the funds in that final app actually clear, because they release the lien rights the moment the waiver is signed. Doing it the other way around — unconditional with the final app — is one of the most expensive lien-rights mistakes a sub can make, because the GC gets a release of lien before they have actually paid.

Why do pay apps stall on the GC / owner rep desk?

Six reasons account for most stalls. (1) The G703 lines don't reconcile to the G702 totals. (2) Stored-materials values are claimed without a bill of sale or insurance rider. (3) Retainage is calculated inconsistently from the contract / schedule-of-values (often vs. AIA default 10%). (4) Lien waivers are missing, or a conditional / unconditional pairing is wrong — most often an unconditional right where a conditional belongs. (5) Schedule-of-values line names don't match the GC's master SOV, so the owner rep can't trace the line. (6) The owner's lender / construction loan draw date is missed, which sends the whole billing cycle forward to the next draw.

What's the difference between a billable minute and the pay app itself?

A billable minute is one Clockify-tracked minute we spend on the paperwork — billing it at $45/hr to the exact minute, no rounding, no pad. The pay app itself is the deliverable (the G702 + G703 PDF, signed, paired with the right conditional waiver). The invoice line for one pay app usually shows a handful of small tasks — pulling the schedule of values, building the G703 lines, applying retainage, attaching the conditional waiver — each on its own Clockify line, each billed at its actual duration. Most pay apps ship in 30-90 minutes of total time; the invoice you receive reconciles to the Clockify entries behind it.

TL;DR

The 30-second version.

  • G702 is the cover sheet, G703 is the continuation / schedule-of-values breakdown — every G703 line rolls up to a G702 total.
  • Subs file monthly, on the schedule the subcontract sets — usually tied to the GC billing cutoff and the owner lender draw date.
  • Conditional waivers ship with every pay app. Unconditional waivers ship only AFTER the corresponding funds actually clear.
  • Six mistakes stall pay apps: G703-to-G702 mismatch, missing stored-materials backup, wrong retainage math, mispaired waivers, off SOV-naming, and missing the lender draw date.
  • We build and submit the full stack — billed at $45/hour to the exact minute through Clockify — and the invoice reconciles line-by-line to the time behind it.
Who this helps

For subcontractors.

Prepare payment applications with the line-item support, waivers, and backup that help the GC review and release funds faster.

Explore support for subcontractors
Send the PO and the timer starts

Stop chasing the GC's desk. Start the Clockify timer.

Drop the contract or scope in the inbox and we'll build the next pay app on the cadence your GC set — at $45/hour, billed to the exact minute, every minute visible on the invoice before the line amount is ever printed. Most requests are accepted within one business day.

$45/hour · Clockify-tracked · billed to the exact minute
Read next
Subcontractors

The paperwork that costs subs the most.

Construction bookkeeping for subcontractors: pay apps, lien-waiver prep, and the cash-flow gap that bleeds working capital between draws.

Services

The full service menu — $45/hour, billed to the minute.

Pay apps, lien waivers, A/R follow-up, virtual bookkeeping — Clockify-tracked, exact-minute billing, no minimums. One rate, one time trail.